# Agam · Construction Journal

Recorded costs: 3761099.00 INR. 111 recorded worked days; at least 490 worker-days. Unknown attendance remains unknown. Costs include construction, financing and site improvement; approvals and paperwork costs are listed as individual cost records with scope "paperwork" and are not part of this build total. They are not a completion budget.

## Monthly costs

| Month | Amount (INR) |
| --- | ---: |
| 2026-03 | 656675.00 |
| 2026-04 | 131000.00 |
| 2026-05 | 322200.00 |
| 2026-06 | 341360.00 |
| 2026-07 | 482600.00 |
| 2026-08 | 437400.00 |
| 2026-09 | 741300.00 |
| 2026-10 | 510764.00 |
| 2026-11 | 110300.00 |

Only supported month-level costs appear here; undated, billing-cycle and cumulative costs stay outside this allocation.

## Cost categories

| Category | Amount (INR) |
| --- | ---: |
| Civil labour | 1163700.00 |
| Reinforcement steel | 860300.00 |
| Sand & aggregates | 395050.00 |
| Red bricks | 278300.00 |
| Cement | 228900.00 |
| Concrete placement labour | 101200.00 |
| Shed / warehouse | 80000.00 |
| Timber formwork boards | 78000.00 |
| Borewell work | 76900.00 |
| Earthmoving | 73900.00 |
| Commercial electricity | 65635.00 |
| Loan charges | 45000.00 |
| Tipper and tractor hire | 42000.00 |
| Architect fees | 41750.00 |
| Teak tree cutting | 30000.00 |
| Labour food & snacks | 21575.00 |
| Elevation ring | 21000.00 |
| CCTV & Wi-Fi setup | 20000.00 |
| Electrical work | 17989.00 |
| Cement blocks | 15990.00 |
| Curing-water motor & cable | 15000.00 |
| Electrical setup | 15000.00 |
| Waterproofing | 13010.00 |
| Electrical work labour | 13000.00 |
| Material transport | 12300.00 |
| Carpentry labour | 10000.00 |
| Tank water supply | 9800.00 |
| Misc | 7500.00 |
| Small concrete & shuttering supplies | 6500.00 |
| Painting labour | 1800.00 |

## Reported stage

Lintel approximately 8 ft and walls approximately 11 ft above the basement floor. Roof cast: yes.
Stated basement depth: 7 ft. Stated slab thickness: 6 in.
Roof work: Roof centering, TMT rod placement; reported as of 2026-10-03.

## Read the records

[Search public records](/developers/#first-request) · [Agent guide](/agents.md) · [About](/about/) · [Privacy](/privacy/)

## Source

- Owner construction history report · September 2026; recorded 2026-09 (month precision).
- Owner progress and spend report · 28 September 2026; recorded 2026-09-28 (day precision).
- Owner-confirmed March–September account · 3 October 2026; recorded 2026-10-03 (day precision).
- Owner-reported omitted costs and scope clarifications · 3 October 2026; recorded 2026-10-03 (day precision).
- Owner clarification of curing-water motor and electricity cycles · 3 October 2026; recorded 2026-10-03 (day precision).
- Owner-supplied construction terminology and borewell dimensions · 3 October 2026; recorded 2026-10-03 (day precision).
- Owner clarification of cost months and site status · recorded 4 October 2026; recorded 2026-10-04 (day precision).
- Owner roof preparation, attendance and cost update · recorded 4 October 2026; recorded 2026-10-04 (day precision).
- Owner voice report of the day's crew, hours and work · recorded 6 October 2026; recorded 2026-10-06 (day precision).
- Owner report of a porch roof-slab centering payment · recorded 7 October 2026; recorded 2026-10-07 (day precision).
- Owner voice report of the day's crew and work · recorded 7 October 2026; recorded 2026-10-07 (day precision).
- Owner report of plan approval fees · 8 Oct 2026; recorded 2026-10-08 (day precision).
- Owner report of site facts · 8 Oct 2026; recorded 2026-10-08 (day precision).
- Owner report of a material transport payment · 8 Oct 2026; recorded 2026-10-08 (day precision).
- Owner note on brands, stock and cement payments · 9 October 2026; recorded 2026-10-09 (day precision).
- Owner answers on the SAT Enterprise ledger · 17 Oct 2026; recorded 2026-10-17 (day precision).
- Site journal · labour payments, 12–17 Oct 2026; recorded 2026-10-17 (day precision).
- Site journal · labour payments, 23–25 Oct 2026; recorded 2026-10-27 (day precision).
- Site journal · electrical materials, 13–25 Oct 2026; recorded 2026-10-27 (day precision).
- Site journal · cement stock, purchase and use, 29 Sep–27 Oct 2026; recorded 2026-10-27 (day precision).
- Site journal · mestri presence, 29 Sep 2026; recorded 2026-10-27 (day precision).
- Site journal · electrical work payment, 31 Oct 2026; recorded 2026-10-31 (day precision).
- Site journal · roof spend, 1–31 Oct 2026; recorded 2026-10-31 (day precision).
- Owner clarification of stage section levels · recorded 1 November 2026; recorded 2026-11-01 (day precision).
- Owner payment report · 2 Nov 2026; recorded 2026-11-02 (day precision).
- Owner payment report · 5 Nov 2026; recorded 2026-11-05 (day precision).
- Owner payment report · 6 Nov 2026; recorded 2026-11-06 (day precision).
Review: not independently reviewed. Last updated: 2026-11-13.