title: "Ravanan Kudil construction journal"
description: "Recorded costs: 3132535.00 INR. 80 recorded worked days; at least 356 worker-days. Unknown attendance remains unknown. Costs include construction, paperwork, financing and site improvement; they are not a completion budget."
canonical: https://home.ashwingopalsamy.in/
last_updated: 2026-10-04
revision: 471cec0b93d1c63e227c67f68e53b5bd1ec4a2186d9416aed1b6d80848dba360
language: en
---

# Ravanan Kudil construction journal

Recorded costs: 3132535.00 INR. 80 recorded worked days; at least 356 worker-days. Unknown attendance remains unknown. Costs include construction, paperwork, financing and site improvement; they are not a completion budget.

## Monthly costs

| Month | Amount (INR) |
| --- | ---: |
| 2026-03 | 656675.00 |
| 2026-04 | 131000.00 |
| 2026-05 | 322200.00 |
| 2026-06 | 341360.00 |
| 2026-07 | 482600.00 |
| 2026-08 | 437400.00 |
| 2026-09 | 741300.00 |

Only supported month-level costs appear here; undated, billing-cycle and cumulative costs stay outside this allocation.

## Cost categories

| Category | Amount (INR) |
| --- | ---: |
| Civil labour | 887200.00 |
| Reinforcement steel | 804700.00 |
| Red bricks | 278300.00 |
| Earthmoving / aggregates, unspecified | 207000.00 |
| Cement | 169600.00 |
| Earthmoving | 115900.00 |
| Concrete placement labour | 101200.00 |
| Sand & aggregates | 82240.00 |
| Shed / warehouse | 80000.00 |
| Borewell work | 76900.00 |
| Commercial electricity | 65635.00 |
| Loan charges | 45000.00 |
| Architect fees | 41750.00 |
| Teak tree cutting | 30000.00 |
| Elevation ring | 21000.00 |
| CCTV & Wi-Fi setup | 20000.00 |
| Labour food & snacks | 20000.00 |
| Cement blocks | 15000.00 |
| Curing-water motor & cable | 15000.00 |
| Electrical setup | 15000.00 |
| Waterproofing | 13010.00 |
| Carpentry labour | 10000.00 |
| Tank water supply | 9800.00 |
| Small concrete & shuttering supplies | 6500.00 |
| Painting labour | 1800.00 |

## Reported stage

Lintel approximately 8 ft and walls approximately 11 ft above the basement floor. Roof cast: no.
Stated basement depth: 7 ft. Stated slab thickness: 6 in.
Roof work: Roof centering, TMT rod placement; reported as of 2026-10-03.

## Read the records

[Search public records](/developers/#first-request) · [Agent guide](/agents.md) · [About](/about/) · [Privacy](/privacy/)

## Source

- Owner construction history report · September 2026; recorded 2026-09 (month precision).
- Owner progress and spend report · 28 September 2026; recorded 2026-09-28 (day precision).
- Owner-confirmed March–September account · 3 October 2026; recorded 2026-10-03 (day precision).
- Owner-reported omitted costs and scope clarifications · 3 October 2026; recorded 2026-10-03 (day precision).
- Owner clarification of curing-water motor and electricity cycles · 3 October 2026; recorded 2026-10-03 (day precision).
- Owner-supplied construction terminology and borewell dimensions · 3 October 2026; recorded 2026-10-03 (day precision).
- Owner clarification of cost months and site status · recorded 4 October 2026; recorded 2026-10-04 (day precision).
Review: not independently reviewed. Last updated: 2026-10-04.