title: "Reinforcement steel"
description: "240000.00 INR; Mar 2026. Month-level recording, not an individual payment day."
canonical: https://home.ashwingopalsamy.in/records/cost-2026-03-11/
last_updated: 2026-10-03
revision: 4bbc36def109aaf5c2c72cc161cf61f910328ea121fb74340b72a339805bbade
language: en
---

# Reinforcement steel

240000.00 INR; Mar 2026. Month-level recording, not an individual payment day.

## Recorded cost

- Amount: 240000.00 INR (24000000 paise).
- Category: reinforcement-steel. Scope: construction.
- Coverage: Mar 2026. Precision: month.

## Source

- March 2026 notebook expense lines · transcription recorded 3 October 2026; recorded 2026-10-03 (day precision).
Review: source_checked. Last updated: 2026-10-03.
Freshness comes from source/correction dates; month-only sources use their publication date as a disclosed release-date fallback. Work and payment dates are separate.

[Canonical page](https://home.ashwingopalsamy.in/records/cost-2026-03-11/) · [Developer guide](/developers/) · [Navigation](/llms.txt)