title: "Labour for electrical pipework and setup on the roof, done on 24 Oct before the roof concrete on 25 Oct"
description: "13000.00 INR; 31 Oct 2026. Recorded at day precision."
canonical: https://home.ashwingopalsamy.in/records/electrical-labour-2026-10-31/
last_updated: 2026-10-31
revision: 7ff905058ebeddc17cfd16c0505e73cc1227a0fa84c66723389a3656192bd024
language: en
---

# Labour for electrical pipework and setup on the roof, done on 24 Oct before the roof concrete on 25 Oct

13000.00 INR; 31 Oct 2026. Recorded at day precision.

## Recorded cost

- Amount: 13000.00 INR (1300000 paise).
- Category: electrical-labour. Scope: construction.
- Coverage: 31 Oct 2026. Precision: day.

## Source

- Site journal · electrical work payment, 31 Oct 2026; recorded 2026-10-31 (day precision).
Review: owner_reviewed. Last updated: 2026-10-31.
Freshness comes from source/correction dates; month-only sources use their publication date as a disclosed release-date fallback. Work and payment dates are separate.

[Canonical page](https://home.ashwingopalsamy.in/records/electrical-labour-2026-10-31/) · [Developer guide](/developers/) · [Navigation](/llms.txt)